Brief
Talk on the Application of Light Material Replacement Technology for Lateral
Direction Hole of Embankment in Bump at Bridge-Heading Control
Yanming Feng
Chongqing
Jiaotong University, Chongqing, 400074, China
Abstract:
With the rapid economic development of coastal areas in China, local highway construction
is also booming. Due to the vertical and horizontal of underground rivers in
coastal areas of China, soft soil foundation is widely distributed. The uneven
settlement of roadbed occurs continuously in the built operational highway. One
of the most typical problems is the bumping at the bridge head. This roadbed
disease seriously affects the safety and comfort of vehicles. The bumping
caused by vehicles passing through the bumping section at the bridge head will
further deepen the uneven settlement of roadbed. In the treatment of soft foundation,
the settlement of embankment can be treated by transverse orifice diversion on
both sides of embankment and replacement of light soil with air bubbles, which
can ensure that the existing highway can maintain the diseased sections without
enclosed traffic and reduce the economic losses caused by enclosed traffic due
to road construction.
Keywords:
Bubble light soil; Embankment lateral pilot hole; Operated highway; Bump at
bridge-head; Unclosed traffic